Fossil Bay, Bracklesham Bay

Reserved Matters Planning Permission was approved at Land South of Clappers Lane for (Appearance, Landscaping, Layout and Scale) details and approval of Conditions 13 (Sustainable Design and Construction Statement) and 19 (Landscaping details) of outline permission E/20/03125/OUT, for the erection of up to 100 dwellings with associated access, landscaping and public open space.


 

Project Timeline


•Archaeological Works - Works have been completed to the site before our works commenced. No significant findings.


•Site Commencement - Commenced

•Sales Launch - Summer 2025

•First Occupation - Autumn / Winter 2025

•S278 Works - January 2025 *Subject to road space and local highways

•Site Completion - Winter 2027 / 2028